Finsbury Leisure Centre Redevelopment

Decision Maker: Executive

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Decision:

RECOMMENDATIONS:

 

Subject to ongoing gateway reports and financial viability assessments, to:

2.1 Note the increased project cost since Stage 2 and the project’s risk mitigation strategy including the retention of £32.7m in contingency (26% of net scheme cost) 2.2 Approve proceeding to Stage 4 based on Stage 3 Design and Viability Assessment.

2.3 Approve £4.6m additional funding for consultant and direct fees and PCSA fees until the end of Stage 4, mainly to cover increased requirements under the Building Safety Act, noting total forecast fee spend to end of stage 4 is £14.55m. Page 126 2.4 Note the costed risk included in the cost model plus the addition of optimism bias to cover additional risk not fully mitigated within the costed risks.

2.5 Note that while the FLCR scheme is based on a low carbon, policy compliant design, the gas[1]powered EC1 Energy Centre will be removed from the FLC&R site, its future to be resolved as part of a separate strategy for a borough-wide heat network (including Bunhill) that will form a future paper to Executive, also noting the issues set out in section 3.8.

2.6 Note the intention to develop of a wellbeing offer for local residents to take advantage of the co[1]location of leisure and medical facilities.

2.7 Note the full General Fund deficit of £31.029m and Housing Revenue Account (HRA) deficit of £3.187m based on current total cost including all contingencies.

2.8 Approve re-allocation of £6.55m of General Fund capital programme borrowing to FLCR, as set out in para 3.7.20 to mitigate additional revenue pressures of up to £0.711m per annum.

2.9 Note the intention to engage with the GLA to assess any opportunities to secure additional grant to support the affordable housing within the scheme.

2.10 Note that additional Executive approval will be sought prior to award of a construction contract at RIBA Stage 5

 

 

 

DECISIONS

 

AGREED RECOMMENDATIONS

 

Reasons for the decision – as detailed in the report

Other options considered – as detailed in the report

Conflicts of interest / dispensations granted none

Publication date: 18/07/2024

Date of decision: 18/07/2024

Decided at meeting: 18/07/2024 - Executive

Effective from: 24/07/2024