AGREED RECOMMENDATIONS
Reason for decision – as specified in the report.
Other options considered - none.
Conflicts of interest/dispensations granted – none.
Minutes:
RESOLVED:
2.1 That procurement of contract
1819-0029a failed because no bidders
met the
minimum requirements at ITT stage be noted.
2.2 That the revised procurement strategy for the operation, delivery and
facilities management of Islington’s 11
adventure playgrounds for up to
15 years
as outlined in this report (an initial 3-year contract followed
by
4
opportunities to extend by 3 years at a time (15 = 3+3+3+3+3))
and
to note
that the recommended contract length will maximise
opportunities for levering in additional revenue and capital funds
over
the
15-year period, providing much needed additional resource to
support
facilities management and capital improvement across the
adventure playground estate be agreed.
2.3 That authority to award the
contracts be delegated to the Corporate
Director
of People in consultation with the Executive Member for
Children, Young People and Families be agreed.
Reason for decision – to ensure continuity of the Adventure Play provision.