New lease for substation in relation to new build scheme at Hathersage and Besant Court

Meeting: 09/06/2022 - Executive (Item 911)

911 New lease for substation in relation to new build scheme at Hathersage and Besant Court pdf icon PDF 390 KB

Additional documents:

Decision:

AGREED RECOMMENDATIONS

Reasons for decision – to facilitate the new build scheme and ensure continued power supply to the area

Other options considered – none

Conflicts of interest / dispensations granted – none

 

Minutes:

RESOLVED:

 

To grant a lease for a substation to London Power Networks plc for 99 years at peppercorn rent, as detailed in the report submitted.

 

Reasons for decision – to facilitate the new build scheme and ensure continued power supply to the area

Other options considered – none